Projects 22 November 2026 1 min read Gbogbah Matthew Tarr 6 views
WellDone Group completes 46 km road aggregate programme ahead of rainy season

The final consignment of graded base course was released this month, closing a twelve-month aggregate supply programme along the Kakata–Bong Mines corridor.

Delivering against a laying programme

Aggregate supply is rarely constrained by production capacity alone. The harder problem is synchronisation: material has to reach seventeen stockpile points in the sequence the contractor intends to lay it, and it has to be graded to specification when it arrives.

Our production scheduling was rebuilt around the contractor's laying programme rather than our own crushing convenience. Each consignment was held until grading verification cleared it, and released against a stockpile call-off rather than a fixed calendar.

Weather as a planning input

Two extended rain periods interrupted haulage. Because stockpile buffers had been sized for exactly this, laying continued through both. Eleven of twelve monthly targets were met in full; the twelfth closed within the following two weeks.

What carries forward

The programme confirmed something we already suspected: on long infrastructure contracts, predictability outperforms unit price. Clients can plan around a supplier who delivers what was promised, and that planning value compounds across a programme.

Comments (0)

No comments yet. Be the first to share your thoughts.

Leave a comment

Comments are reviewed before they appear. Your email address is not published.

Stay informed

Project updates, tenders and company news — a few times a month, no more.